Aviation Fuel Pipeline Contract, Major UK Airport
| Client: |
Confidential |
| Location: |
South East England, U.K. |
| Date: |
2003 - 2004 |
| Project: |
Aviation Fuel Pipeline Contract |
The project involved the construction of new fuel storage and transmission facilities on a major UK Airport. It comprised the construction of a new tank farm installation, intended to supply aviation fuel (Kerosene, Jet A-1) from two newly constructed fuel receipt facilities through two new airport transfer pipelines.
Abricon were commissioned to undertake the foundation designs for the three main works areas, the two fuel receipt facilities, the tank farm as well as the 2km long pipeline route.
Information collected from the initial geophysical and environmental site investigation indicated that three of the six 26 metre diameter tanks proposed at the tank farm were constructed over an old gravel borrow pit.
The variable thickness of the Made Ground and the dense nature of the Terrace Gravels found on-site had a direct impact on the chosen piling/foundation methodology. Abricon therefore designed the piling/foundation layout to accommodate differential settlement.
The role of Abricon was to record on site and report on the following:
- Anticipated differential settlement under the edge and centre of the tanks.
- Construction advice to minimise differential settlement.
- Recommendations regarding piling across the transition boundary of the gravel pit “high wall”.
- Assessing the minimum factors of safety incorporating any potential creep due to cyclic loading of the fuel tanks.
- Preparation of working method statements for the earthworks contractor.
- Special working methods statements to prevent site staff exposure to any contamination encountered in the made ground.
The whole project was managed within the exacting requirements of the overall contract, within budget and completed on time.
|