Abricon Homepage
Home About Us Our Services Case Studies Knowledge Store Contact
Compliance & Business Improvement
Environmental Permitting for Major Water Supply Company, UK
 
Due Diligence audit, Aerospace Sector, UK
 
Due Diligence audit of Hazardous Waste Operations, UK
 
Due Diligence audit of Industrial Gases business, UK/GER, Pre-acquisition
 
Due Diligence audit of Industrial Gases business, GER, Pre-divestment
 
IPPC Support, Electronics Component manufacturer, UK
 
IPPC Support, Consumer Goods Packaging company, UK
 
SHE Management System development, including oil spill response procedures, Russian Fed
 
EIA and ES for Thermal Decoupling Unit, UK
 
Brownfield, Waste & Geotechnical Environmental Compliance Resource Efficiency Ecological Solutions
Case Studies - Environmental Compliance

IPPC Support, Electronics Component manufacturer, UK

Client: Confidential
Location: Dorset, U.K.
Date: 2002 - 2003
Project: Environmental Site Assessment (ESA), Phase 1 and 2 plus support to obtain IPPC authorisation for a company manufacturing electronic components

Abricon initially carried out a Phase 1 ESA as part of due diligence investigations for the client, who had recently acquired the site.

Subsequently, the new management requested Abricon to assist the company to obtain an IPPC authorisation for its operating processes. An invasive Phase 2 ESA was carried out to enable the client to prepare a baseline contamination report as part of the Site Report required to submit a
permit application.

In addition, Abricon provided assistance to the client to carry out a review of BAT (Best Available Technique) applied at the site to minimise releases to all three environmental media; as support for the IPPC application.